- Milestone 1
- Iteration 1 (Dec. 1, 2008 - Dec. 19, 2008) - OPENJPA-800
- Iteration 1a (Dec. 22, 2008 - Jan. 2, 2009) - OPENJPA-831
- Iteration 2 (Jan. 5, 2009 - Jan. 23, 2009) - OPENJPA-807
- Milestone 2
- Iteration 3 (Jan. 26, 2009 - Feb. 13, 2009) - OPENJPA-808
- Iteration 4 (Feb. 16, 2009 - Mar. 6, 2009) - OPENJPA-875
- Iteration 5 (Mar. 9, 2009 - Apr. 3, 2009) - OPENJPA-956
- Iteration 6 (Apr. 6, 2009 - May 1, 2009) - OPENJPA-1007
- Iteration 7 (May 4, 2009 - May 29, 2009) - OPENJPA-1052
- Milestone 3
- Beta
- Beta 2 - Released Feb. 27, 2010
- Branch - target is March 19, 2010
- Release Candidate - Date TBDtarget is April 12, 2010
|
|
Iteration Tasks
The individual tasks and status can be fond on the JPA 2.0 Tasks page.
...