Date | Milestone | ||
---|---|---|---|
Week of 7 Sep 2020 | Create the 2.0.0-test branch - Done. | ||
While the scope is fluid, we would be rebasing this test branch from master. After we completely freeze the scope, we would only cherrypick commits from Airflow Master to v2-0-test branch if they are “in-scope”. Normal development would continue on Master branch i.e. PRs would be created against Airflow Master. | |||
Week of 12 Oct 2020 | First Airflow 2.0 alpha release "apache-airflow-2.0.0.a1" cut on Oct 13th. | ||
Week of 26 Oct 2020 | Second Airflow 2.0 alpha release "apache-airflow-2.0.0.a2" cut on Oct 26th. | ||
Week of 9 Nov 2020 | Cut first 2.0 beta release. | ||
Beta snapshots would be published to the Airflow Community to test and create issues to make sure Airflow is functioning and backwards compatible outside of known changes. | |||
Week of 16 Nov 2020 | Cut bridge release based on 1.10.x - jump-off point to 2.0. Probably 1.10.13 or 1.10.14 containing upgrade check scripts for 2.0 | ||
Week of 16 Nov 202010 Nov - 7 Dec | Cut second 2.0 beta release | Week of 23 Nov 2020 | Cut third 2.0 beta releasebeta releases approximately every Tuesday. |
Week of 7 Dec 2020 | Cut first 2.0 release candidate (2.0.0rc1) | ||
As part of creating the release candidate, an official vote would be started to release 2.0.0. If there are any bugs discovered in 2.0.0rc1, they will be fixed and a new release candidate will be published. This will be repeated until the Vote passes |
...