The first step to be done to enter scope finalization phase it to create a branch in Ignite code base (origin). This moment be precisely the same with as the start of P1.1 

1.2.1. Create release branch, e.g ignite-2.8, push it to the ASF repository. (optional) consider creating PR for release, having PR is convinient convenient because GitHub will notify you about commits to the branch.

...

1.2.4. Create scheduled build triggers for daily Run All (Nightly) run. Usually, triggers are set up using Apache Ignite TeamCity Bot (triggering of builds there depends on agent availability). Use an intellectual trigger to trigger release branch adaptively, or ask on the dev. list to add.

1.2.5. Create/schedule the nightly release build triggering – Releases Apache Ignite Nightly (may require TC permissions).

End of this phase is scope freeze.  

...

This phase is some time to complete the implementation of features from the initial scope. In parallel with implementation, some less essential fixes and features are moved to the next release. 

End of rampdown ramp-down is code freeze. Code freeze is based on dates, but the actual time of freeze is determined by announcing.

...