Steps

Tasks

Goal

Actual

Comments

Code Freeze and release startTrack ongoing PRsMay 14thMay 14th
Cut the release branchCheck license headersMay 15thMay 15th

Cut the release branch

May 17th

May 17th

Make code changes with necessary version updates on v1.xMay 18thMay 18th
Test the release and tag the releaseNightly test, Jenkins CIMay 19thMay 19th

RAT checkMay 19thMay 19th

Tag RC0May 20thMay 20th
Package artifacts and validateCreate release artifactsMay 21stMay 21st

Validate release packageMay 21stMay 21st

Test release packageMay 21stMay 21st
Begin apache votingStart vote on dev@May 21stMay 21st

Start vote on general@June 2ndJune 9th
Finalizing and posting the releaseCreate the final release tag on githubJune 15th


Rename, resign and upload the src tar to final dirJune 15th


Update the website using tagJune 16th


Release the official pip packageJune 18th


Release the official docker imagesJune 18th


After 24 hrs, validate the packages are uploadedJune 19th


Draft the official announce email and reviewJune 21st


Send out the email on announce@June 21st


Update the apache blogJune 21st


Update the AWS blogJune 21st


Send internal announcementJune 21st

...