Numbers are based on the items in the list below, not on the tickets 


(big grin)(tick) (green star)(star)(red star)(minus)(question)(blue star)Remaining weeks
2023-11-28
29




209
2023-12-12








7
2023-12-26








5
2024-01-09








3
2024-01-23








1

List

Feel free to add categories.

...

  • Is Google Meet OK for everyone?  - ok
  • The release sync meeting time, currently Europe has gone into winter time(CET, UTC+1), is 9am ok? - ok
  • Daily work divisions
    • JIRA ticket (Mainly focus on new blockers, progress of existing blockers each week) lincoln lee 
    • CI (Failures reported in #build channel and not reported) Martijn Visser 
    • Benchmark (Check if there's regression in the #flink-dev-benchmarks channel) Yun Tang 
    • Mailing list monitoring Jing Ge 
    • This division doesn't mean that other RMs are now allowed to do the work. All RMs should take responsibilities on all of these daily issues if they are available. 
  • Feature freezing date. - Jan 26, 2024, 00:00 CET(UTC+1) 
  • Retrospective of 1.18

11/28/2023

  • Blockers
    • Jira
      serverASF JIRA
      serverId5aa69414-a9e9-3523-82ec-879b028fb15b
      keyFLINK-25857
        discuss thread
    • documentation build failures
      Jira
      serverASF JIRA
      serverId5aa69414-a9e9-3523-82ec-879b028fb15b
      keyFLINK-33544