0.20 Release
Status
- 1 November: Alpha 2 is cut at revision 1404590 of trunk
- 1 November: Beta is postponed to 14 November
- 25 October: Alpha is cut at revision 1402191 of trunk
- 9 July: Trunk is open for 0.20 development at revision 1359193
...
Alpha | http://people.apache.org/~jross/qpid-0.20-alpha/![]() |
Alpha 2 | http://people.apache.org/~jross/qpid-0.20-alpha2/![]() |
Links
None
Schedule
17 October
...
31 October, 2 weeks later
- Alpha 2
31 October 14 November, 2 weeks later
- Beta
- The release branch is created
- Trunk opens for development toward the next release
- Release branch commits require approval
- Release manager produces outstanding bug report and triages bugs
14 November 28 November, 2 weeks later
- RC1
21 November 5 December, 1 week later
- RC2
28 November 12 December, 1 week later
- RC3
- Targeted release date