With a less than a week left before code freeze for the 4.2 release on 7/29, there is a lot of work still to be done and a lot of bugs that need to be worked out. With this major release many new and existing features need the blocker and critical bugs cleared out as soon as possible. There's been great teamwork in the community. Animesh Chaturvedi points out the work that still needs to be done:

...For the days remaining to code freeze, lets prioritize fixing blockers and critical over majors. As from last week in order to clear up our backlog I request you to help out on aggressively fixing the issues. The unassigned issue list is available at http://s.apache.org/BlH/. When you fix a bug in 4.2 please make sure it is also fixed in master.

The outstanding resolved issues now stand at 492 with 250 blockers and critical still to be verified. As with fixing issues now we need to focus on blockers and critical first.

The detailed bug status is captured below.

Bugs

This Week

 

 

 

Last Week

 

 

 

 

Blocker

Critical

Major

Total

Blocker

Critical

Major

Total

Incoming

29

48

64

144

31

40

46

120

Outgoing

37

68

51

159

33

38

65

140

Open Unassigned

6

13

149

208

6

46

120

226

Open Total

24

68

239

392

30

84

213

388

The status for features or improvement is depicted in table below

New Features / Improvements

Today

Last Week

Closed

13

12

Resolved

60

59

In Progress

9

10

Reopened

2

2

Ready To Review

0

0

Open

18

19

Total

102

102

...