Status | Timeline item | ||
---|---|---|---|
Past | 00:01, Saturday, 25th Apr 2015 PDT : Deadline for call for patches for general purpose feature inclusion.(must have patch-available already to request for feature inclusion after this) 00:15, Saturday, 25th Apr 2015 PDT : Branch creation for branch-1.2. | Current | 12:01, Monday 27th Apr 2015 PDT : Work begins on rolling out RC0 - the purpose of RC0 will be to test out that we're able to go through the process of making a release candidate, and will likely not include all the bugfixes planned for this release. 00:01, Tuesday, 28th Apr 2015 PDT : Deadline for call for patches for feature inclusion if the features are near end-of-development. (only bugfixes allowed after this). Non-bugfix JIRAs that have already been requested for inclusion before this time, that have not yet been resolved will not be affected, we will still treat them as blockers for the eventual release. |
Current | <working on getting RC0 ready> | ||
Future | 00:01, Tuesday, 28th Apr 2015 PDT : Deadline for call for patches for feature inclusion if the features are near end-of-development. (only bugfixes allowed after this). Non-bugfix JIRAs that have already been requested for inclusion before this time, that have not yet been resolved will not be affected, we will still treat them as blockers for the eventual release. 12:01, Wednesday, 29th Apr 2015 PDT : Current tracking time for community availability of RC0. 15:01, Thursday, 30th Apr 2015 PDT : Deadline for call for patches for inclusion for bugfixes that have a workaround (only critical bugfixes that do not have workarounds allowed after this), intended deadline for committing all feature request patches. 16:01, Thursday, 30th Apr 2015 PDT : Work begins on rolling out RC1 - the purpose of RC1 will be to be the first actual release candidate, and include all the feature commits and any bugfix commits that have happened so far. Full test run intended on RC1, with community verification. 16:01, Friday, 1st May 2015 PDT : Current tracking time for community availability of RC1. |
JIRAS requested to be included in 1.2 release after RC0 preparation begins
Requirement : Bugfixes only
Deadline for inclusion : 15:01, Thursday, 30th Apr 2015 PDT
Status : Open for inclusion
Category | JIRA | Current Status for 1.2 | Committer requesting inclusion | ||||||
---|---|---|---|---|---|---|---|---|---|
Testing Infrastructure |
| patch-available | sushanth | ||||||
JIRAS requested to be included in 1.2 release after 1.2 branch creation, but before RC0 roll outs
...
Deadline for inclusion : 00:01, Tuesday, 28th Apr 2015 PDT
Status : Open for inclusion List frozen, all jiras in this list will be honoured for inclusion to Hive 1.2 and are approved for commit to branch-1.2.
Category | JIRA | Current Status for 1.2 | Committer requesting inclusion | ||||||
---|---|---|---|---|---|---|---|---|---|
Transactions |
| patch-available | alangates | ||||||
HBase Handler |
| committed | ashutoshc | ||||||
CBO |
| committed | ashutoshc | ||||||
Logical Optimizer |
| committed | ashutoshc | ||||||
QL |
| committed | jdere | ||||||
Metastore |
| patch-available | vgumashta | ||||||
Logging |
| committed | jdere | ||||||
hadoop-1 |
| committed | prasanthj | ||||||
hadoop-1 |
| committed | prasanthj | ||||||
hadoop-1 |
| committed | prasanthj | ||||||
hadoop-1 |
| committed | prasanthj | ||||||
serde |
| patch-available | jdere | ||||||
jdbc |
| committed | thejas | ||||||
orc |
| patch-available | omalley | ||||||
metastore |
| patch-available | thejas | ||||||
Tez/MR configs |
| bugfix : in-progress | thejas | ||||||
QL |
| patch-available | prasanthj | ||||||
build & release |
| committed | sushanth | ||||||
metastore |
| patch-available | sushanth | ||||||
HCatalog |
| patch-available | sushanth | ||||||
Testing Infrastructure |
| patch-available | sushanth | ||||||
JIRAS requested to be included in 1.2 release before 1.2 branch creation (list now closed)
...