In total there 42 items that must be reviewed during the first quarterly call. Following is a schedule on how we are setting the time aside for each company based on number of things they have listed:
Development Discussion - start time 9:05 AM PST
ShapeBlue - 14 items
Accelerite - 8 items
ENA - 2 items
CloudOps - 2 items
Nuage - 6 items
Community Discussion
ShapeBlue - 5 Items
Accelerite - 5 Items
Development Efforts:
Listed in the order communication was received.
...
Summary Support Hyper-V Clustering.
Link to FS and/or JIRA None
Lead Developer
Release target
Company: CloudOps
Feature Name Baremetal using MaaS
Lead Developer Syed Ahmed
Summary We want to add baremetal functionality in Cloudstack for advanced networks using MaaS which offers a wide varity of options for provisioning baremetal servers.
Summary Generic network and VPC migration support to a new Physical network (and new network/vpc offering), tested for Native to Nuage networks deployments and v.v.
Short Summary CloudStack installation has huge dependency on distro provided tomcat, by moving to embedded jetty (like we do use jetty for development) we can sync how developers develop/test mgmt servers and users use it. In addition, it will be easier to publish pkgs without depending on distro provided dependencies.
Lead(s) R Yadav/MA Brothier
Target Date
Subject Debian9 systemvmtemplate
Short Summary Required update, Debian7 is EOL, moving to Debian9 will give; newer kernel, newer packages, Smaller disk footprint (faster deployment and more space efficient) and Systemd should give quicker boot time
Lead(s) R Yadav/W Hollander
Target Date
Subject 4.9.3.0
Short Summary Backport of bug fixes to 4.9 branch and release 4.9.3.0.
Lead(s) R Yadav
Target Date
Subject Winston
Short Summary WIP - PoC of Phase 1 (consolidated data storage) in ShapeBlue Lab - Elasticsearch instance receiving test run data from Trillian & Blue Orangutan. Once it has a decent amount I'll come to community for ideas and feedback (and help). By the time of the conf call I will have updated: https://cwiki.apache.org/confluence/display/CLOUDSTACK/Project+Winston+-+Consolidated+Test+Data
Lead(s) P Angus
Target Date
Subject Marvin Test Categories
Short Summary Enable quicker, targeted test runs in Marvin, by allowing user to specify Which element(s) are touched ie. Networking
Lead(s) B Stoyanov
Target Date
Company: Accelerite
Subject Release Management
Short summary Accelerite has been doing Release management for many releases for Cloudstack. Most recently 4.10. We will continue these efforts
Lead(s) Rajani
Target date
Subject PR Process
Short summary Current PR process takes quite a long for a PR to get merged. Couple of examples (1) there are comments on the PR that were addressed by the author but no one may respond (2) there are comments from reviewers and the author does not respond. The whole process can take potentially a longtime if either the author or the reviewers take time to respond. Can we think about implementing some kind of validating on the Prs.. Bottomline is how can we improve ?
Lead(s) TBD
Target date
Subject Regression Tests
Short Summary There are a number of tests in the integration folder which are not run. Need to group these together and start running them.
Lead(s) Raja/Looking for support
Target Date TBD
Subject Release Qualification
Short Summary RC to Readiness takes quite a bit of time. Can we discuss on ways to improve this.
Lead(s) Raja/Looking for support
Target Date TBD
Subject Performance Testing
Short Summary Add Performance tests. Need hardware where we can run these tests on?