The project administrator has full access over all projects in the system and , can perform all the actions of all rolestasks of any projectmanager and additionally can:

  • Create new projects and assign a project manager
  •  maintain skill types
  • maintain resources in the resources manager.

Project manager Role.

How to setup a project?The project manager is responsible for one or more projects and can perform the following functions:

  1. Create or make sure a proper Resource list exist by selecting existing parties in the project resources tab.
  2. Create a project with related phases and tasks or copy these from a template.
  3. Add resources from the resourcelist to the project.
  4. Add planned start and end/dates and estimated hours required (a scheduler is planned)
  5. Start the project and let everybody register their time in the mytime option.
  6. Monitor on a weekly basis the registered hours.
  7. Monitor the planned versus actual dates in the project.
  8. Create invoices at the end of the month from the entered timesheets.

Please note that this is an application in development and comments are welcomed, either in Jira as a request or at the bottom of the page.

...