This wiki page is used to display the current status of this project. This page will be updated frequently with the current updates of the project. A separate thread in the Tuscany-dev list will be used for the regular discussions about the project.
...
Time Period | Task |
---|---|
22nd April 2008 - 29th April 2008 | Getting Familiar with Apache Tuscany, Apache Geronimo and other related technologies |
30th April 2008 - 25th May 2008 | Coming up with the finalized list of features and a design. Defining a list of test scenarios |
26th May 2008 - 5th July 2008 | First Phase of the development |
6th July 2008 | Mid-term evaluation |
15th July 2008 - 04th August 2008 | Second Phase of development |
04th August 2008 - 17th August 2008 | Documentation, Code Reviews and testing the different scenarios defined in the designing phase |
18th August 2008 | Final Evaluation |
Current Process | Going through the documentation again, Getting more familiar with the Tuscany source Implementation phase 1. |
Project Log
21 st April 2008 - Got Accepted.
...
6th July 2008 - Added the User Interfaces related to the Tuscany to the ACE. Submitted a few patches containing the changes done. Next step is to add the real functionality to the ACE while improving the UIs. It took some time to figure out how a JSP can be called within an another JSP in a portlet. This was not straight forward, as portlets have some abstractions from the underlying servlets. I could find only one article which described this matter. But it was a bit brief, so I had to go through the code to figure out the exact way to implement it.