Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.


Excerpt


Start DateDescription
2018-

...

09-

...

25Preparation - schedule, pages, Synergy (

...

2 days)
2018-

...

09-27NetCAT 10.0 invitation sent, volunteers start joining
2018-

...

09-

...

28Creation of tribes (

...

4 days)
2018-

...

10-

...

02Review of existing test specs and creation of new ones where required (

...

1 week)
2018-

...

10-

...

08Full testing of beta build starts (

...

3 weeks)
2018-

...

10-

...

29Community Acceptance survey opened (

...

2 weeks)
2018-11-05PPMC thread for 1st vote candidate started
2018-

...

11-

...

09NetBeans

...

10.0 GA build check (3 days)
2018-11-12NetCAT satisfaction survey (4 days)
2018-

...

11-

...

15NetBeans

...

10.0 GA ready for release
2018-

...

11-16NetCAT 10.0 closed