Start DateDescription
2018-09-25Preparation - schedule, pages, Synergy (2 days)
2018-09-27NetCAT 10.0 invitation sent, volunteers start joining
2018-09-28Creation of tribes (4 days)
2018-10-02Review of existing test specs and creation of new ones where required (1 week)
2018-10-08Full testing of beta build starts (3 weeks)
2018-10-29Community Acceptance survey opened (2 weeks)
2018-11-05PPMC thread for 1st vote candidate started
2018-11-09NetBeans 10.0 GA build check (3 days)
2018-11-12NetCAT satisfaction survey (4 days)
2018-11-15NetBeans 10.0 GA ready for releasereleased
2018-11-16NetCAT 10.0 closed


...