Start DateDescription
2019-02-01Preparation - schedule, pages, Synergy (3 days)
2019-02-04NetCAT 11.0 invitation sent, volunteers start joining
2019-02-07Synergy test run prepared,
2019-02-11Tribes updated, test assignments created (1 per participant), testing starts on vc1
2019-02-21Request to switch to vc2 sent
2019-02-251/2 way sync-up with tribe leaders
2019-03-07Request to switch to vc3 sent
2019-03-11Community Acceptance survey launched for vc3
2019-03-18Certification completed, blockers fixed in vc4 or waived
2019-03-22Community Acceptance survey closed and results published, satisfaction survey launched
2019-03-28Apache NetBeans 11.0 released
2019-03-29Satisfaction survey closed and results published, NetCAT 11 closed


...