Following table captures a list of work items to be completed for a successful release. This list will evolve in the first few meetings but should stabilize as we approach the release dates. Also, specific tasks would eventually translate into JIRAs.
Version Consensus:
As per the suggestions on the mailing list, the initial release will be 1.0.0-incubating.M1 similar to how Spring projects use releases. This may be followed by one or subsequent milestone releases (.M2, M3, etc). As stability improves and the community determines the project is ready we can prepare a final release candidates 1.0.0-incubating.RC1, .RC2, etc and finally 1.0.0-incubating.RELEASE.
# | Activity | Tasks | Alpha(s) | M#.RC1 | M#.RC2Release Candidate | ... |
---|---|---|---|---|---|---|
1 | Scope & Preparation |
| ||||
2 | Packaging & Signing Release Check |
| ||||
3 | Voting & Approvals |
| ||||
4 | Publishing & Announcements |
|
Following table describes the alpha first milestone (M1) scope and steps, to be voted as Release Candidate 1:
Category | Work Item | Owner | ETA | Status | Notes (updates/ risks/ etc) | |||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Preparation |
| Nitin Lamba | Oct 02 | Done | Agile Board | |||||||||||||||
Preparation |
| Nitin Lamba | Dec 07 | Done | Updated Release management & Release process pages | |||||||||||||||
Scope |
| Bruce Schuchardt | Nov 20 | Done | Merged into develop | |||||||||||||||
Scope |
| Dick Cavender | Dec 31 | Done | includes RAT | |||||||||||||||
Scope |
| Anthony Baker | Dec 31 | Done | licensing fixes; related to RAT | |||||||||||||||
Scope |
| Anthony Baker | Dec 01 | Done | findbugs annotation resolved. | |||||||||||||||
Scope |
| Anthony Baker | Dec | Done | Generate source artifacts | |||||||||||||||
Preparation | Version: 1.0.0-alpha1incubator.M1 | Community | Jan 11 | Done | ||||||||||||||||
Review |
| ?Anthony Baker | [Jan 15] | Open | Done | Fixed with RC1 feedback | ||||||||||||||
Preparation | Release Branch in Git: 1.0.0-incubator.M1 Create JIRA version 1.0.0-incubator.M1 Update the versionNumber in gradle.properties | Release Manager | [Jan 12] | In ProgressDone | Git: | version created. Needs updateComplete JIRA: | version created. Needs updateComplete Gradle: | Needs updateRelease process captured on Wiki | ||||||||||||
Preparation | All Tests pass/ Nightly builds stable | Kirk Lund | ? | OpenOK. Optional | CI (pre-checkin DUnit) tests are still unstable. | |||||||||||||||
Packaging | Release Notes: | External?(not packaged with src tarball) | Release Manager | [Jan 15] | Open | Two versions in JIRA - needsDone | Needs review/ clean-up: | 1.0.0-incubating | : here1. | 0.0-incubating.M1: here|||||||||||
Internal Review | Validate Release checklist items | Release Manager | Jan 12 | In Progress | Pending GEODE-610. | |||||||||||||||
M1 Notes are generated from JIRA here | ||||||||||||||||||||
Signing | Preparing for Code signing
| Release Manager | Jan 15 | Done | Signing | Preparing for Code signing | PMC Member? | Generate KEYS file listing all the committers. | ||||||||||||
Signing | Signing src artifacts | Release Manager | ||||||||||||||||||
PMC Review | ||||||||||||||||||||
Voting | PMC vote and publishing | RM/ Mentor? | Voting | |||||||||||||||||
Publishing | Artifacts in Maven Repo | Release Manager | ||||||||||||||||||
Announcement | Announce to mailing lists/ etc | Release Manager |
And following table captures the activities for the Release Candidate after the trial run:
Category | Work Item | Owner | ETA | StatusScope | Notes (updates/ risks/ etc) |
| 386
| Anthony Baker | Done | Decide if in scope | Scope||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Publishing | Documentation/ fixes on website
| 36
| David Barnes/ Karen Miller | Done | Website fixes complete. Docs needing final version/ review | |||||||||||||||||||||||||||
Publishing | Decide if in scope | Scope | Artifacts in Maven Repo |
| 37
| Release Manager | Decide if in scope | |||||||||||||||||||||||||
Preparation | Version: 1.0.0-incubating.M2 | |||||||||||||||||||||||||||||||
Preparation | Release Branch in Git Rename the JIRA version to 1.0.0-incubating.M2 Update the versionNumber in gradle.properties | Release Manager | ||||||||||||||||||||||||||||||
Preparation | All Tests pass/ Nightly builds stable | Kirk/ Anil? | ||||||||||||||||||||||||||||||
Packaging | Release Notes | Mark Bretl | ||||||||||||||||||||||||||||||
Done | Release bits parked: https://repository.apache.org/content/repositories/orgapachegeode-1001/ | |||||||||||||||||||||||||||||||
Internal Review | Validate Release checklist items | Release Manager | Jan 16 | |||||||||||||||||||||||||||||
Signing | Code signing for artifacts | Release Manager | ||||||||||||||||||||||||||||||
PMC Review | ||||||||||||||||||||||||||||||||
Done | Pending GEODE-610. | |||||||||||||||||||||||||||||||
Voting | PMC vote and publishing | RM/ Mentor?Release Manager | Done | Voting | ||||||||||||||||||||||||||||
Publishing | Artifacts in Maven Repo | Release Manager | ||||||||||||||||||||||||||||||
PMC Review | Validating artifacts for Release Candidate 1 | Jan 17-25 | Done | Good feedback | ||||||||||||||||||||||||||||
Review & Fix | Publishing
| 53
| -54
| All | Jan 20-27 | Done | Fixed blocker issues | |||||||||||||||||||||||||
Voting | PMC vote and publishing | Release Manager | Jan 27 | Done | Sent VOTE e-mail | |||||||||||||||||||||||||||
PMC Review | Validating artifacts for Release Candidate 2 | Jan 27-31 | Done | |||||||||||||||||||||||||||||
Announcement | Announce to mailing lists/ etc | Release Manager |