Start Date | Description |
---|
2020-02-18 | Preparation - schedule, pages, Synergy (3 days) |
2020-02-21 | NetCAT 12.0 invitation sent, volunteers start joining |
2020-03-02 | Review of test specifications (2 weeks) |
2020-03-13 | Synergy test run prepared |
2020-03-16 | Official 6-weeks certification starts on beta1 |
2020-03-30 | Request to switch to beta2 |
2020-04-03 | 1/2 way sync-up with tribe leaders |
2020-04-13 | Request to switch to beta3 |
2020-04-27 | Community Acceptance 2-weeks survey launched for beta3 |
2020-05-04 | Certification completed, blockers fixed in vc or waived |
2020-05-08 | Community Acceptance survey closed and results published |
2020-05-08 | Sanity check of Apache NetBeans 12.0 GA build (4 days) |
2020-05-12 | Apache NetBeans 12.0 GA voting thread started (3 days) |
2020-05-15 | Apache NetBeans 12.0 released |
2020-05-15 | NetCAT 12.0 Satisfaction survey (1 week) |
2020-05-22 | NetCAT 12.0 closed |