Status
- 3 June 2014: Qpid 0.28 is generally available
- 13 May 2014: Proposed final RC2 is available at revision 1594179 of the release branch
- 24 April 2014: RC1 is available at revision 1589856 of the release branch
- 10 April 2014: Beta 2 is available at revision 1586009 of the release branch
- 20 March 2014: Beta is available at revision 1579693 of the release branch
- 20 March 2014: The release branch is created at revision 1579686
- 5 March 2014: Alpha is available at revision 1574236 of trunk
- 12 November 2013: Trunk is open at revision 1541273
...
Links
Change approval process
Changes to the release branch require approval. The approval has two parts:
...
- The release branch is created
- Release branch commits require approval
- Trunk opens for development toward the next release
Beta 2: 9 April
RC1: 12 March 26 March 16 April, 1 week later
- Documentation is staged for release
- Preliminary release notes and documentation are available for review
- Release manager produces outstanding bug report
- Only important defects are considered for inclusion
RC2: 19 March 2 April 23 April, 1 week later
RC3: 26 March 9 April 30 April, 1 week later
- Targeted release date