Timing
Planned | Actual | |
Planning Phase | Dec 17 - Jan 7 | Dec 17 - Jan 18 |
Announce Release | Jan 7 | Jan 18 |
QA | Jan 7 - Jan 21 | Jan 28 - Feb 1 |
Publish Release Notes | Jan 21 | Feb 1 |
Vote on Release | Jan 28 | Feb 8 |
Target Release Date | Feb 5 | Feb 15 |
Scope
There are main goals of this release
- Share the pull requests and features that have been contributed by several partner organizations
- Share the APIs built for external contributors that haven't been shipped yet
- Share the features from 1.4 that didn't ship in 1.4.
- Share any critical bug fixes and minor enhancements.
Possible Features/Tasks to Ship
- Changes contributed by Partners including:
- Enhancements led by Mifos, developed by DPC with support from DIAL
- GSOC Hardening
- Partner Contributions
Release Artifacts
Release Notes (JIRA Link: )
Task
List out...
Wish
List out...