Release timelines:

Following timeline is based on everything goes well.(Added some buffer time)

StepTasksCompleted byComments
Code Freeze and release startTrack ongoing PRsNovember 27, 2018




Cut the release branchCheck license headersNovember 29, 2018Depending on stability

Make code changes with necessary version updatesNovember 29, 2018

Cut the release branchNovember 29, 2018

Update the version on masterNovember 29, 2018
Test the release and tag the releaseNightly test, Jenkins CIDecember 4, 2018

RAT checkpart of CI

Tag RC0





Package artifacts and validateCreate release artifactsDecember 6, 2018

Validate release packageDecember 6, 2018

Test release packageDecember 6, 2018

Scala release process





Begin apache votingStart vote on dev@December 7, 2018

Start vote on general@December 11, 2018




Finalizing and posting the releaseCreate the final release tag on githubDecember 17, 2018

Rename, resign and upload the src tar to final dirDecember 17, 2018

Update the website using tagDecember 17, 2018

Release the official pip packageDecember 17, 2018

Release the official docker imagesDecember 17, 2018

After 24 hrs, validate the packages are uploadedDecember 18, 2018

Draft the offical announce email and review


Send out the email on announce@December 18, 2018

Update the apache blogDecember 18, 2018

update the aws blogDecember 18, 2018

send internal announcementDecember 18, 2018