r


Target releaseContributor Survey 2.0
Epic

Document status

Document owner
DesignerN/A
Developers

N/A

QAN/A


Goals

Background and strategic fit

This project will help us achieve our short term goals (2019): 

Considerations

Requirements and Timeline

Milestones for the Bitergia Analytics consultancy are throughout a 6-month project:

Note: Dates assume a start date and kickoff by September 16, 2019.

Requirements by Milestone

Completion Date

Milestone 1 - Survey Design

  • Include relevant CHAOSS D&I WG metrics and survey questions.
  • Feedback collected in a 1-hour session with ASF members. One week before, draft survey submitted to dev@diversity.apache.org.
  • ASF pilots the survey with ComDev and incubator for one week.
  • Final survey is provided to ASF, ready to begin data collection.

Nov 15, 2019

Milestone 2 - Survey Data Collection

  • ASF distributes the survey to its members.
  • ASF reminds its members to take the survey to achieve 10% response rate (750 responses) or more.
  • Survey is open from Dec 2nd until Dec 20th, then assess if we open it until Jan 12th. 

Mar 13, 2020

Milestone 3 - Initial Survey Analysis

  • Survey responses are analyzed.
  • Initial results are shared with ASF as a presentation in a 1-hour session. Slides are shared on dev@diversity.apache.org.
  • Initial results inform the design of interviews.

Jun 26, 2020

Milestone 4 - Interview Preparation

  • Include relevant CHAOSS D&I WG metrics and interview questions.
  • Design questions to elicit reactions to the initial survey results.
  • Identify projects of interest in collaboration with ASF.
  • Recruit informants from those projects with help from ASF.
  • Interview questions submitted to dev@diversity.apache.org.

Jun 26, 2020

Milestone 5 - Conduct Interviews

  • 20 interviews are conducted.

Aug 3, 2020

Milestone 6 - Analysis of Interviews

  • Working session to define a structure for analysis and reports.
  • Qualitative analysis of interviews.
  • Interview results, together with quantitative analysis results, are shared with ASF as a presentation in a 1-hour session. Slides are shared on dev@diversity.apache.org.

Sep 4 , 2020

Milestone 7 - Quantitative Analysis

  • Use of Bitergia technology to observe diverse in contribution data.
  • Use of relevant CHAOSS metrics.
  • Validation of survey and interview findings with evidence from contribution data. 
  • Quantitative analysis results, together with interview results, are shared with ASF as a presentation in a 1-hour session. Slides are shared on dev@diversity.apache.org.

Sep 14, 2020

Milestone 8 - Final Report

  • Written documentation and discussion of findings from surveys, interviews, and quantitative analysis.
  • Structure is oriented around CHAOSS guidelines and best practices.
  • Lessons learned and experiences shared with CHAOSS community.
  • Final report shared with ASF on dev@diversity.apache.org.

Oct 16, 2020

Questions

Below is a list of questions to be addressed as a result of this document:

AuthorQuestionAnswer/Outcome
ldap(e.g. How we make users more aware of this feature?)Communicate the decision reached