Status

Issues

Distributions

Links

Change approval process

Changes to the release branch require approval. The approval has two parts:

To request a change after beta, post your request to the mailing list. Put "RFI" (request for inclusion) and the requested release in the subject. Make sure the change has a JIRA, so the reviewer and release manager can record their approvals, rejections, or other comments there. Any changes requested should be consistent with the acceptance criteria listed below.

In general, a change for the release branch should be important (if it's not important, we'll get it in the next release) and safe (not liable to cause disruption or instability).

Change acceptance criteria

Schedule

Alpha - 13 July 2016

Beta - 10 August 2016 27 July 2016, 2 weeks later

RC - 17 August 2016, 1 week later

Additional alphas, betas, or RCs may be inserted as needed.