Previous: 0.28 Release
Next: 0.32 Release
 

Status

 

  • 20 March 2014: Trunk is open at revision 1579686
     

    Issues

     
    None
     

    Distributions

     
    None
     

    Links

     
    None
     

    Change approval process

     
    Changes to the release branch require approval. The approval has two parts:
     
  • Review by a developer other than the original contributor
  • Approval by the release manager
     
    To request a change after beta, post your request to the mailing list. Put "RFI" (request for inclusion) and the requested release in the subject. Make sure the change has a JIRA, so the reviewer and release manager can record their approvals, rejections, or other comments there.

Any changes requested should be consistent with the acceptance criteria listed below. In general, a change for the release branch should be important (if it's not important, we'll get it in the next release) and safe (not liable to cause disruption or instability).
 

Change acceptance criteria

 

  • Trunk open to Alpha: Developers work at their own discretion
  • Alpha to Beta: Major features, improvements, or refactorings need discussion before they can go in; bug fixes are unencumbered
  • Beta to RC: Bug fixes only; exceptions are sometimes made for improvements that are important, isolated, and small in terms of code delta
  • After RC: Bug fixes for important defects only, such as build failures, regressions, or security vulnerabilities
     

    Schedule

     
    Alpha: 2 July 2014
     
  • Major feature integration ends; with approval, certain less disruptive features can be committed
  • Trunk remains open for bug fixing
  • The alpha release tests the release process after the introduction of major features
     
    Beta: 16 July 2014, 2 weeks later
     
  • The release branch is created
  • Release branch commits require approval
  • Release manager produces outstanding bug report
  • Trunk opens for development toward the next release
     
    RC: 30 July 2014, 2 weeks later
     
  • Preliminary release notes and documentation are available for review
     
    Additional alphas, betas, or RCs may be inserted as needed.