Target releaseContributor Survey 2.0
Epic

Jira
serverASF JIRA
serverId5aa69414-a9e9-3523-82ec-879b028fb15b
keyDI-27

Document status

Status
subtletrue
titleDRAFT

Document owner
DesignerN/A
Developers

N/A

QAN/A


Goals

  • Get consensus on project scope for survey re-design and contributor experience research project

...

Note: Dates assume a start date and kickoff by September 16, 2019.

Description of Deliverables

Completion Date

Milestone 1 - Survey Design

  • Include relevant CHAOSS D&I WG metrics and survey questions.
  • Feedback collected in a 1-hour session with ASF members. One week before, draft survey submitted to dev@diversity.apache.org.
  • ASF pilots the survey with ComDev and incubator for one week.
  • Final survey is provided to ASF, ready to begin data collection.

Oct 15, 2019

Milestone 2 - Survey Data Collection

  • ASF distributes the survey to its members.
  • ASF reminds its members to take the survey to achieve 10% response rate (750 responses) or more.
  • Survey is open
for four weeks (Oct 16 - Nov 13), including during ApacheCon Europe (Oct 21 - Oct 24).
  • from Dec 2nd until Dec 20th, then assess if we open it until Jan 12th. 

Jan 12, 2020

Nov 14, 2019

Milestone 3 - Initial Survey Analysis

  • Survey responses are analyzed.
  • Initial results are shared with ASF as a presentation in a 1-hour session. Slides are shared on dev@diversity.apache.org.
  • Initial results inform the design of interviews.
Nov

Jan 27,

2019

2020

Milestone 4 - Interview Preparation

  • Include relevant CHAOSS D&I WG metrics and interview questions.
  • Design questions to elicit reactions to the initial survey results.
  • Identify projects of interest in collaboration with ASF.
  • Recruit informants from those projects with help from ASF.
Feedback collected in a 1-hour session with ASF members. One week before, interview
Dec 6

Feb 9,

2019

2020

Milestone 5 - Conduct Interviews

  • 20 interviews are conducted.
Dec 20

Mar 8,

2019

2020

Milestone 6 - Analysis of Interviews

  • Working session to define a structure for analysis and reports.
  • Qualitative analysis of interviews.
  • Interview results, together with quantitative analysis results, are shared with ASF as a presentation in a 1-hour session. Slides are shared on dev@diversity.apache.org.
Jan 17

Apr 5 ,

2019

2020

Milestone 7 - Quantitative Analysis

  • Use of Bitergia technology to observe diverse in contribution data.
  • Use of relevant CHAOSS metrics.
  • Validation of survey and interview findings with evidence from contribution data. 
  • Quantitative analysis results, together with interview results, are shared with ASF as a presentation in a 1-hour session. Slides are shared on dev@diversity.apache.org.
Jan 17

Apr 5,

2019

2020

Milestone 8 - Final Report

  • Written documentation and discussion of findings from surveys, interviews, and quantitative analysis.
  • Structure is oriented around CHAOSS guidelines and best practices.
  • Lessons learned and experiences shared with CHAOSS community.
  • Final report shared with ASF on dev@diversity.apache.org.
Jan 31

May 8,

2019

2020

Questions

Below is a list of questions to be addressed as a result of this document:

AuthorQuestionAnswer/Outcome
ldap