Page properties |
---|
Target release | Contributor Survey 2.0 |
---|
Epic | Jira |
---|
server | ASF JIRA |
---|
serverId | 5aa69414-a9e9-3523-82ec-879b028fb15b |
---|
key | DI-27 |
---|
|
|
---|
Document status | |
---|
Document owner | |
---|
Designer | N/A |
---|
Developers | N/A |
---|
QA | N/A |
---|
|
Goals
- Get consensus on project scope for survey re-design and contributor experience research projectDescribe the requirements and timeline of the research project to understand the state of diversity and inclusion in the ASF.
Background and strategic fit
This project will help us achieve our short term goals (2019):
Jira |
---|
server | ASF JIRA |
---|
serverId | 5aa69414-a9e9-3523-82ec-879b028fb15b |
---|
key | DI-25 |
---|
|
...
Considerations
- A contributor survey and a contributor experience research will give us a complete picture of the current status of D&I and it's main root causes
- We'll be able to draw recommendations and map gaps we can address in our medium term goals
...
Requirements and Timeline
Milestones for the Bitergia Analytics consultancy are throughout a 6-month project:
Note: Dates assume a start date and kickoff by September 16, 2019.
Description of DeliverablesRequirements by Milestone | Completion Date |
Milestone 1 - Survey Design - Include relevant CHAOSS D&I WG metrics and survey questions.
- Feedback collected in a 1-hour session with ASF members. One week before, draft survey submitted to dev@diversity.apache.org.
- ASF pilots the survey with ComDev and incubator for one week.
- Final survey is provided to ASF, ready to begin data collection.
|
Oct Nov 15, 2019 |
Milestone 2 - Survey Data Collection - ASF distributes the survey to its members.
- ASF reminds its members to take the survey to achieve 10% response rate (750 responses) or more.
- Survey is open
|
for four weeks (Oct 16 - Nov 13), including during ApacheCon Europe (Oct 21 - Oct 24).- from Dec 2nd until Dec 20th, then assess if we open it until Jan 12th.
| Mar 13, 2020 |
Nov 14, 2019 |
Milestone 3 - Initial Survey Analysis - Survey responses are analyzed.
- Initial results are shared with ASF as a presentation in a 1-hour session. Slides are shared on dev@diversity.apache.org.
- Initial results inform the design of interviews.
|
Nov 27 20192020 |
Milestone 4 - Interview Preparation - Include relevant CHAOSS D&I WG metrics and interview questions.
- Design questions to elicit reactions to the initial survey results.
- Identify projects of interest in collaboration with ASF.
- Recruit informants from those projects with help from ASF.
|
Feedback collected in a 1-hour session with ASF members. One week before, interview Dec 6 20192020 |
Milestone 5 - Conduct Interviews - 20 interviews are conducted.
|
Dec 20 20192020 |
Milestone 6 - Analysis of Interviews - Working session to define a structure for analysis and reports.
- Qualitative analysis of interviews.
- Interview results, together with quantitative analysis results, are shared with ASF as a presentation in a 1-hour session. Slides are shared on dev@diversity.apache.org.
|
Jan 17 20192020 |
Milestone 7 - Quantitative Analysis - Use of Bitergia technology to observe diverse in contribution data.
- Use of relevant CHAOSS metrics.
- Validation of survey and interview findings with evidence from contribution data.
- Quantitative analysis results, together with interview results, are shared with ASF as a presentation in a 1-hour session. Slides are shared on dev@diversity.apache.org.
|
Jan 17 20192020 |
Milestone 8 - Final Report - Written documentation and discussion of findings from surveys, interviews, and quantitative analysis.
- Structure is oriented around CHAOSS guidelines and best practices.
- Lessons learned and experiences shared with CHAOSS community.
- Final report shared with ASF on dev@diversity.apache.org.
|
Jan 31 2019 Questions
Below is a list of questions to be addressed as a result of this document:
Author | Question | Answer/Outcome |
---|
ldap | | |